SPCC Plan Builder Free check

Home / SPCC for construction yards

GC, owner or lender asking for your yard's SPCC plan? Build it from your tank list

EPA's quick-settlement form for small facilities lists a $1,750 penalty just for having no SPCC plan. A case that goes to court can cost far more (the law allows up to $59,114 a day, 40 CFR 19.4).

If a general contractor, lender or permit reviewer wants the plan before work starts, that date is your deadline. The free check takes about two minutes; you see your own plan before you pay, and the documents are generated within minutes of checkout.

An engineer's SPCC plan: $1,500 to over $10,000 (Texas A&M AgriLife Extension) or $2,000 to $4,000 (Purdue Extension); farm extension estimates from 2011 and 2013, the most recent published ranges we could verify. Sources: Texas A&M AgriLife Extension EBN-001 (2013), Purdue Extension via Farm and Dairy (2011). Ours: from $299, one time.

  • Free eligibility check first
  • Editable DOCX and PDF
  • Every requirement cited to 40 CFR
  • Missing-element guarantee, plus 30 days no questions asked

The short answer

An equipment yard with a diesel tank, a fuel truck and some drums is covered when the counted total is more than 1,320 gallons (40 CFR 112.1(d)(2)(ii)) and a spill could reach water. Your machines' own fuel tanks do not count, but the fuel truck does: Any onboard bulk storage container used primarily to power the movement of a motor vehicle, or ancillary onboard oil-filled operational equipment (excluding oil drilling or workover equipment, including rigs), is exempt and not counted. An onboard bulk storage container used to store or transfer oil for further distribution, such as a fuel or service truck, is not a motive power container. The transfer of fuel or other oil into a motive power container at an otherwise regulated facility is not eligible for this exemption. (40 CFR 112.1(d)(7))

A plan has to be in place before a new facility starts operating: A facility other than a farm or an oil production facility that becomes operational after 2011-11-10, and could reasonably be expected to have a discharge as described in 40 CFR 112.1(b), must prepare and implement its Plan before it begins operations. (40 CFR 112.3(a)(1)) If a general contractor, lender or permit reviewer is asking for it before work starts, that is the deadline to plan around.

Tanks you will see in a yard, and what the plan says about each

Shop-built double-wall ASTs

A double-wall tank can serve as its own secondary containment when specific conditions are met: Following EPA guidance (SPCC Guidance for Regional Inspectors, section 4.4.5), a shop-fabricated double-wall aboveground tank is relied on as its own secondary containment (an equivalent system under 40 CFR 112.7(c), and for sized bulk storage containment) because: it is shop fabricated; the inner tank is a UL-listed steel tank; the outer tank is constructed in accordance with nationally accepted industry standards; it is equipped with an overfill alarm and an automatic flow restrictor or flow shut-off (or, as an alternative, active or passive secondary containment for the typical failure mode and most likely quantity of oil discharged from the tank's vents during transfer operations); and all product transfers are constantly monitored. (EPA SPCC Guidance for Regional Inspectors sec. 4.4.5, pp. 4-37 to 4-38)

The double wall does not catch an overfill during a delivery: The double wall contains a leak from the inner tank but not an overfill from the vent during filling. Transfer areas serving double-wall tanks have their own containment or active measures, and piping and equipment outside the tank need general secondary containment. (EPA SPCC Guidance for Regional Inspectors sec. 4.4.5, pp. 4-37 to 4-39)

Inspections: This Plan uses STI SP001, Standard for the Inspection of Aboveground Storage Tanks, as the industry standard for inspecting and testing its shop-built aboveground containers that are within the scope of that standard. As EPA's guidance describes the standard, it assigns each tank a category based on its size, whether it is in contact with the ground, whether it has secondary containment or spill control, and whether it has a continuous release detection method; the category sets the type and frequency of the owner's periodic inspections and of formal external and internal inspections by a certified inspector. Formal inspection intervals: per industry standard (STI SP001 category for this container). (40 CFR 112.8(c)(6)) For each double-wall tank, the frequent inspection includes checking the interstitial space (through an inspection port, drain plug, sensor or leak indicator) for oil from the inner tank. Oil found in the interstice is corrected under the industry standard. (40 CFR 112.8(c)(6))

Single-wall tanks in a dike

Secondary containment for the bulk storage containers (including mobile or portable oil storage containers, but not mobile refuelers or other non-transportation-related tank trucks) holds the capacity of the largest container plus additional capacity to contain precipitation. (40 CFR 112.6(a)(3)(ii)) The plan shows the arithmetic for each dike, including the space taken up by other tanks inside it. Try the containment calculator.

Uncontaminated rainwater is drained from a diked area into a storm drain, or effluent is discharged into an open watercourse, lake or pond bypassing the facility treatment system, only if: the bypass valve is normally kept sealed closed; the retained rainwater is inspected to ensure its presence will not cause a discharge as described in 40 CFR 112.1(b); the bypass valve is opened and resealed following drainage under responsible supervision; and adequate records of each drainage event are kept in the dike drainage log. (40 CFR 112.8(c)(3))

Fuel trucks and fuel trailers

Mobile refuelers (as defined in 40 CFR 112.2) and other non-transportation-related tank trucks are excepted from sized bulk storage containment, but remain subject to general secondary containment under 40 CFR 112.7(c) for the typical failure mode and most likely quantity of oil discharged, such as sorbents or curbing. As EPA guidance explains, the exception from sized containment does not apply to vehicles used primarily to store oil in a stationary location. (40 CFR 112.7(c))

Drums and totes of hydraulic oil, motor oil and grease

Mobile or portable oil storage containers are positioned or located to prevent a discharge as described in 40 CFR 112.1(b). Except for mobile refuelers and other non-transportation-related tank trucks, they are inside secondary containment that holds the entire capacity of the largest single container plus additional capacity to contain precipitation (see the bulk storage containment requirement). (40 CFR 112.6(a)(3)(ii))

Large tanks

One tank over 5,000 gallons moves you from Tier I to Tier II (40 CFR 112.3(g)(1)); more than 10,000 gallons in total means a PE must certify the plan (40 CFR 112.3(g)(2)). As EPA guidance notes, for tanks larger than 5,000 gallons most industry standards require more than a visual inspection by the owner or operator; this Plan schedules the formal inspections required by the named industry standard. (40 CFR 112.8(c)(6))

Fueling and deliveries

Temporary and seasonal tanks

Tanks that are only there for a season or a job still count: Containers used for standby, seasonal or temporary storage are covered and counted unless they meet the definition of permanently closed. (40 CFR 112.1(b)(3))

Find out in a few questions whether you need a plan, and which tier

The eligibility check is free and needs no account. You see your result, why, and the rule behind it, before anything is for sale. If you need an engineer, it says so.

Start the free eligibility check
Do I need a Professional Engineer?

Not if your facility is a qualified facility: 10,000 gallons or less of aboveground oil storage, and in the past 3 years no single discharge to water over 1,000 gallons and no two over 42 gallons within 12 months (40 CFR 112.3(g)(2)). Farms have their own limits set by statute; see SPCC for farms.

You do need a licensed PE when: your facility is over those limits (40 CFR 112.3(d)); containment is not practicable somewhere and you want to use alternative measures instead (40 CFR 112.6(b)(4)(i)); or your state limits plan certification to engineers. A PE must visit the site (40 CFR 112.3(d)(1)(ii)), so no document tool can replace one. If the free check finds you need a PE, it tells you why and we do not sell you a plan. To find one, look up licensed engineers through your state's engineering licensing board and ask for SPCC experience.

What if my site is unusual?

The intake asks about each container separately: shop-built or factory, single or double wall, indoors or out, what containment it has, and how it is filled. Anything the rules treat differently (mobile refuelers, oil-filled equipment, double-wall tanks, buried piping, a dike with several tanks in it) gets its own plan text and calculation. Where your answers show a gap, such as containment that is too small, the plan says so on the cover, leaves that item unchecked, and lists the work as its own paragraph with the target date you set, instead of hiding it.

Some situations are outside what a self-certified plan can do, and we say so: oil production facilities, and any spot where you would claim containment is impracticable (40 CFR 112.6(a)(1)(vii)). Those need a PE.

How long does it take?

The free eligibility check is short and needs only your container sizes and spill history. The full intake takes longer, mostly because you need your tank list, the inside dimensions of each dike or curbed area, and your contacts in front of you. You can stop and come back from the emailed link. After payment the documents generate right away, and you can download the DOCX and PDF as soon as they are ready.

If an inspector gave you a deadline, note that EPA's expedited settlement process gives facilities 30 days to correct violations and sign (EPA 2023 SPCC Expedited Settlement memo (2023)).

Related

A document tool, not engineering or legal advice. You, the owner or operator, certify the plan.

Sources cited on this page

Regulation text from the eCFR, quoted verbatim, with the date we last checked it. See how we check sources.

  • 40 CFR 19.4: Civil judicial penalty for failing to comply with SPCC regulations (CWA 311(b)(7)(C)). Checked 2026-11-21.
    “| 33 U.S.C. 1321(b)(7)(C) | CWA | 59,114 | 57,617 | 25,000 |”
  • 40 CFR 112.1(b)(3): Standby, seasonal and temporary storage is still covered. Checked 2026-11-21.
    “Any container that is used for standby storage, for seasonal storage, or for temporary storage, or not otherwise “permanently closed” as defined in § 112.2;”
  • 40 CFR 112.1(d)(2)(ii): Only containers of 55 gallons or more are counted. Checked 2026-11-21.
    “For the purposes of this exemption, only containers with a capacity of 55 U.S. gallons or greater are counted.”
  • 40 CFR 112.1(d)(2)(ii): Aggregate aboveground oil storage threshold. Checked 2026-11-21.
    “The aggregate aboveground storage capacity of the facility is 1,320 U.S. gallons or less of oil.”
  • 40 CFR 112.1(d)(7): Motive power containers are exempt (fuel transfers into them are not). Checked 2026-11-21.
    “Any “motive power container,” as defined in § 112.2. The transfer of fuel or other oil into a motive power container at an otherwise regulated facility is not eligible for this exemption.”
  • 40 CFR 112.3(a)(1): New non-farm facilities need a Plan before operations begin. Checked 2026-11-21.
    “If such a facility (excluding oil production facilities) becomes operational after November 10, 2011, and could reasonably be expected to have a discharge as described in § 112.1(b), you must prepare and implement a Plan before you begin operations.”
  • 40 CFR 112.3(d): A PE must certify the Plan unless the facility qualifies under 112.6. Checked 2026-11-21.
    “Except as provided in § 112.6, a licensed Professional Engineer must review and certify a Plan for it to be effective to satisfy the requirements of this part.”
  • 40 CFR 112.3(d)(1)(ii): PE certification includes a site visit by the PE or agent. Checked 2026-11-21.
    “That he or his agent has visited and examined the facility;”
  • 40 CFR 112.3(g)(1): Tier I: no aboveground container over 5,000 gallons. Checked 2026-11-21.
    “has no individual aboveground oil storage container with a capacity greater than 5,000 U.S. gallons.”
  • 40 CFR 112.3(g)(2): Qualified facility: 10,000 gallons or less aboveground. Checked 2026-11-21.
    “and has an aggregate aboveground oil storage capacity of 10,000 U.S. gallons or less.”
  • 40 CFR 112.3(g)(2): Qualified facility: no single discharge over 1,000 gallons. Checked 2026-11-21.
    “A Tier II qualified facility is one that has had no single discharge as described in § 112.1(b) exceeding 1,000 U.S. gallons”
  • 40 CFR 112.3(g)(2): Qualified facility: no two discharges over 42 gallons within 12 months. Checked 2026-11-21.
    “no two discharges as described in § 112.1(b) each exceeding 42 U.S. gallons within any twelve month period in the three years prior to the SPCC Plan self-certification date”
  • 40 CFR 112.6(a)(1)(vii): Tier I: impracticability is not available. Checked 2026-11-21.
    “The Plan does not deviate from any requirement of this part as allowed by § 112.7(a)(2) and 112.7(d) or include measures pursuant to § 112.9(c)(6) for produced water containers and any associated piping; and”
  • 40 CFR 112.6(a)(3)(ii): Mobile and portable containers: positioned to prevent a discharge (Tier I). Checked 2026-11-21.
    “Position or locate mobile or portable oil storage containers to prevent a discharge as described in § 112.1(b).”
  • 40 CFR 112.6(a)(3)(ii): Bulk storage and mobile containers: largest container plus precipitation (Tier I). Checked 2026-11-21.
    “Construct all bulk storage container installations (except mobile refuelers and other non-transportation-related tank trucks), including mobile or portable oil storage containers, so that you provide a secondary means of containment for the entire capacity of the largest single container plus additional capacity to contain precipitation.”
  • 40 CFR 112.6(a)(3)(iii): Tier I: overfill prevention system or documented procedure. Checked 2026-11-21.
    “Ensure that each container is provided with a system or documented procedure to prevent overfills of the container, describe the system or procedure in the SPCC Plan and regularly test to ensure proper operation or efficacy.”
  • 40 CFR 112.6(b)(4)(i): PE-certified portions (hybrid Plan) are outside this product. Checked 2026-11-21.
    “As described in paragraph (b)(3) of this section, the facility owner or operator may not self-certify alternative measures allowed under § 112.7(a)(2) or (d), that are included in the facility's Plan. Such measures must be reviewed and certified, in writing, by a licensed Professional Engineer.”
  • 40 CFR 112.7(a)(3)(ii): Procedures for routine handling of products. Checked 2026-11-21.
    “Discharge prevention measures including procedures for routine handling of products (loading, unloading, and facility transfers, etc.);”
  • 40 CFR 112.7(c): Mobile refuelers and on-site tank trucks: general containment only. Checked 2026-11-22.
    “Provide appropriate containment and/or diversionary structures or equipment to prevent a discharge as described in § 112.1(b)”
  • 40 CFR 112.7(g): Prevent unauthorized access to oil pump starter controls. Checked 2026-11-21.
    “prevent unauthorized access to starter controls on oil pumps”
  • 40 CFR 112.8(c)(3): Draining rainwater from diked areas. Checked 2026-11-21.
    “Not allow drainage of uncontaminated rainwater from the diked area into a storm drain or discharge of an effluent into an open watercourse, lake, or pond, bypassing the facility treatment system unless you: (i) Normally keep the bypass valve sealed closed. (ii) Inspect the retained rainwater to ensure that its presence will not cause a discharge as described in § 112.1(b). (iii) Open the bypass valve and reseal it following drainage under responsible supervision; and (iv) Keep adequate records of such events”
  • 40 CFR 112.8(c)(6): Shop-built containers: STI SP001 where the Plan names it. Checked 2026-11-21.
    “You must determine, in accordance with industry standards, the appropriate qualifications for personnel performing tests and inspections, the frequency and type of testing and inspections”
  • 40 CFR 112.8(c)(6): Double-wall tanks: inspect the interstitial space. Checked 2026-11-21.
    “In addition, you must frequently inspect the outside of the container for signs of deterioration, discharges, or accumulation of oil inside diked areas.”
  • 40 CFR 112.8(c)(6): Tanks over 5,000 gallons: most industry standards require more than owner visual inspection (EPA guidance). Checked 2026-11-21.
    “Test or inspect each aboveground container for integrity on a regular schedule and whenever you make material repairs.”
  • 40 CFR 112.8(d)(5): Warn vehicles away from aboveground piping and transfers. Checked 2026-11-21.
    “Warn all vehicles entering the facility to be sure that no vehicle will endanger aboveground piping or other oil transfer operations.”
  • EPA SPCC Guidance for Regional Inspectors sec. 4.4.5, pp. 4-37 to 4-38: Shop-built double-wall tanks as secondary containment. Checked 2026-11-21.
    “Shop-fabricated double-wall ASTs, regardless of size, may generally satisfy not only the secondary containment requirements of §112.7(c), but also the specific secondary containment requirements for sizing secondary containment for bulk storage containers found at §112.8(c)(2).”
  • EPA SPCC Guidance for Regional Inspectors sec. 4.4.5, pp. 4-37 to 4-39: Double-wall tanks do not contain vent overfills during transfers. Checked 2026-11-21.
    “A double-walled tank may have adequate containment for the bulk storage container; however it does not provide adequate secondary containment to address”
  • EPA 2023 SPCC Expedited Settlement form (2023): $1,750.
    “Failure to have a Spill Prevention Control and Countermeasure Plan 112.3 ($1,750)”
  • EPA 2023 SPCC Expedited Settlement memo (2023): 30 days.
    “Respondents are given 30 days to return a signed”