Home / Methodology
How plans are built and checked
Accuracy is the product. Here is exactly how a requirement gets from the regulation into your plan, and how we check it.
1. Primary sources, captured and dated
We download the primary sources and keep a dated copy: 40 CFR 112.1 through 112.8 and 112.12 from the eCFR, Appendix G (EPA's Tier I template), EPA's SPCC Guidance for Regional Inspectors, EPA's pages for farms and qualified facilities, the farm provisions of the Water Resources Reform and Development Act of 2014, and the penalty tables in 40 CFR 19.4. Each copy records its URL and the date it was fetched.
2. A rules library, one rule per requirement
Every threshold, requirement, frequency and template section the generator uses is a rule in a machine-readable library. Each rule holds the plain-English text that prints in the plan, any numbers as parameters, the CFR paragraph, the URL, a verbatim quote from the captured source, and the date it was checked. Numbers such as 1,320 gallons or 5 years are never typed into the program; they are read from the rule, so they cannot drift.
- 224 rules in the library today (version sha256-26d7af3cca1308a5)
- Drawn from 16 captured primary sources
- Checked between 2026-11-21 and 2026-11-22
- 224 marked verified by the independent check so far; the release build refuses to publish a plan or page that relies on an unverified rule
Where the regulation and EPA guidance differ, the rule says so. For example, the regulation requires containment for the largest container plus "sufficient freeboard" for rain; the 110% figure is guidance, and the plan states it as the certifier's chosen design criterion (40 CFR 112.8(c)(2)).
3. Automated checks on every build
- Every quote must appear word for word in its captured source, inside the CFR paragraph it cites, or the build fails.
- Every rule must have a citation, a URL that matches the source, and a checked date no earlier than the capture.
- Plan text that states an obligation must carry the id of the rule it came from, and every rule a plan uses prints in its citation appendix.
- This website is built the same way: the requirement text and citations on these pages are pulled from the library at build time. Each page ends with the sources it cites.
4. Independent review
A second AI model, separate from the one that wrote the rules, re-opened each source and checked every quote and paraphrase. Every disagreement was resolved against the source text and logged. Test cases for realistic fictional facilities (a farm, an auto shop, a construction yard, a fuel yard and others) are worked out by hand from the rules and must match the generator's output.
5. What we do not do
- We do not certify plans. This Plan is self-certified by the facility owner or operator under 40 CFR 112.6. It has not been reviewed or certified by a Professional Engineer, and the document tool that helped prepare it does not certify it.
- We are not engineers or lawyers, and we do not give engineering or legal advice. We do not inspect your facility; you must (40 CFR 112.6(a)(1)(ii)).
- We do not sell plans to facilities that need a Professional Engineer (40 CFR 112.3(d)).
- We have no affiliation with EPA or any government agency.
6. When the rules change
When a cited section changes, we re-capture it, update the affected rules, re-run every check and every test case, and regenerate plans for buyers whose plan includes updates. Each plan prints the library version it was built from.
Found an error? Tell us at support@spccplanbuilder.com. We correct it and note the change.
Find out in a few questions whether you need a plan, and which tier
The eligibility check is free and needs no account. You see your result, why, and the rule behind it, before anything is for sale. If you need an engineer, it says so.
Start the free eligibility checkSources cited on this page
Regulation text from the eCFR, quoted verbatim, with the date we last checked it. See how we check sources.
- 40 CFR 112.1(d)(2)(ii): Aggregate aboveground oil storage threshold. Checked 2026-11-21.
“The aggregate aboveground storage capacity of the facility is 1,320 U.S. gallons or less of oil.”
- 40 CFR 112.3(d): Outside the qualified-facility limits a PE must certify. Checked 2026-11-21.
“Except as provided in § 112.6, a licensed Professional Engineer must review and certify a Plan for it to be effective to satisfy the requirements of this part.”
- 40 CFR 112.3(g): The owner or operator certifies, not this product. Checked 2026-11-21.
“The owner or operator of a qualified facility as defined in this subparagraph may self-certify his facility's Plan, as provided in § 112.6.”
- 40 CFR 112.5(b): Review and evaluate the Plan at least once every five years. Checked 2026-11-21.
“complete a review and evaluation of the SPCC Plan at least once every five years from the date your facility becomes subject to this part; or, if your facility was in operation on or before August 16, 2002, five years from the date your last review was required under this part.”
- 40 CFR 112.6(a)(1)(ii): The certifying owner or operator visits and examines the facility (personally, per EPA's FAQ). Checked 2026-11-21.
“You have visited and examined the facility;”
- 40 CFR 112.8(c)(2): 'Sufficient freeboard' is not defined by the rule. Checked 2026-11-21.
“sufficient freeboard to contain precipitation”
- EPA SPCC Guidance for Regional Inspectors sec. 4.3.2 and Figures 4-5 and 4-6, pp. 4-19 to 4-22: Containment sizing calculation (EPA guidance method). Checked 2026-11-21.
“A “110 percent of storage tank capacity” rule of thumb may be an acceptable design criterion in many situations”